Plan for new Main Library

Objective 7A

Finalize all preliminary and planning steps necessary to construct and move into new facility
Supporting Activity Time Frame
Purchase needed properties Contingent on funding
Develop process and plan for project oversight Contingent on funding
Develop and finalize schematic drawing Jan 2010 - Dec 2010
Develop and finalize architectural drawings Contingent on funding
Maintain awareness of technology trends and changes including self check and RFID Jan 2010 - Ongoing
Plan and implement RFID Contingent on funding and/or ground breaking
Plan for furniture and equipment Contingent on funding and/or ground breaking
Develop process and plan for staffing related to project oversight Contingent on funding
Plan for changes related to new organization, staffing and services/features Contingent on funding and/or ground breaking
Plan move Contingent on funding and/or ground breaking
Review and revise policies and procedures in relation to the facility Contingent on funding and/or ground breaking